Travel · Rail, Channel & ferries · 13 November 2026

Merseyrail Northern Line fully reopens after engineering work

Network Rail has confirmed the Merseyrail Northern Line is fully open following four weeks of engineering work. The project involved strengthening and waterproofing four underground tunnels in Liverpool. Trains are now running between Hunts Cross and Liverpool city centre again.

Network Rail has announced that the Merseyrail Northern Line has fully reopened after a period of engineering works. The intervention focused on strengthening and waterproofing four underground tunnels in Liverpool to protect the infrastructure. Paul Owen, Network Rail Liverpool area director, said: "I'd like to thank passengers for bearing with us while we completed this major multi-million-pound investment into the Merseyrail network."

The work, which began on 11 October, involved 50 workers removing 92m² of old concrete. They drilled 6,500 holes for waterproofing injections and 115 weep holes to direct water into drainage systems. A total of 1,688m² of tunnel wall was waterproofed as part of the £3.5m investment.

Trains have been running between Hunts Cross and Liverpool city centre for the first time in 27 days. The railway fully reopened on 7 November. During four extended Sunday closures, power control systems were also modernised across the Northern and Wirral lines.

The upgrades are intended to protect the third-rail system that powers Merseyrail’s electric trains. According to Network Rail, the investment is part of an ongoing plan to make it easier to isolate sections of electrified rail for maintenance. The work is expected to provide more reliable journeys for the millions of passengers who use the Merseyrail network each year.

Stephen Dodd, Merseyrail chief operating officer, noted that the upgrades will strengthen the long-term reliability of the Northern Line. Cllr Steve Foulkes, chair of the Liverpool City Region Combined Authority Transport Committee, added that a reliable rail network is vital to keeping the city region connected.

The original: Railway reopens after four-week £3.5m Merseyrail tunnel upgrades (Network Rail, 7 November 2026)

Written by StreetOwl from Network Rail’s own announcement. It was drafted by StreetOwl’s own model, every figure and quotation was checked by code against the announcement, and it was read and approved by Michael Rossi before it went up. It says what was announced, not what anyone should do about it.